(Source: BC Hydro - British Columbia Hydro and Power Authority) FORT ST. JOHN - This week marks 100 days of construction on the Site C Clean Energy Project in northeast B.C. In the first 100 days of construction, work crews have been undertaking site preparation activities, including: clearing trees and vegetation at the dam site, upgrading public roads, building access roads at the dam site, constructing a 1,600-person worker accommodation facility, excavation and slope stabilization and starting work on a temporary construction bridge across the Peace River. Highlights of the first 100 days of construction include: More than 600 people are currently working on the project and this number...
↧
Site C construction reaches 100-day mark (BC Hydro - British Columbia Hydro and Power Authority) ...
↧